Status of Water Supply Projects under Water Supply Sector, KMDA.

Sl no Name of the project Project code Date of Completion Project cost Fund received expenditure Financial progress % Physical progress % Remarks
JNNURM PROJECTS
1 Surface WS Scheme for Bally Municipality 07/WS/NURM-1/13 Partial commissioned 13849.36 11914.12 11407.06 82.36 74.57  
2 24x7 WS Scheme for Panihati Municipality, Kolkata U.A. 07/WS/NURM-1/14 Partial commissioned 24602.30 15109.76 14695.37 59.73 77.16 Delay due to non-availability of Way leave permission from Rly. Authority.
3 Trans municipal W.S. Project for municipal Towns of Madhyamgram, New Barrackpore and Barasat 08/WS/NURM-1/01 Feb'2016 44547.77 28405.83 24793.37 55.65 56.97 Delay due to non-availability of pipe
4 24x7 WS Project for Dumdum,SouthDumdum and North Dumdum 07/WS/NURM-1/10 commissioned 31272.08 28528.46 28523.61 91.21 90.34 Fund not received.
5 WS Scheme for Bhatpara Municipal Area 07/WS/NURM-1/12 Commissioned 24970.42 21633.41 19044.90 76.27 80.64  
6 Garulia Water Supply 07/WS/NURM-1/09 Commissioned 4719.26 4495.11 3959.47 83.90 93.79  
7 Integration of 30 MGD WTP at Kalyani for catering Gayeshpur, Kanchrapara, Naihati Halisahar & Kalyani. 07/WS/NURM-1/08 Commissioned 17398.11 17398.11 17252.25 99.00 99.00  
8 Water Supply Scheme for Bhadreswar Municipality 07/WS/NURM-1/13 Mar'2016 8877.28 2108.35 2061.61 23.22 29.80 Delay due to non-availability of Pipe
STATE FUND PROJECTS
9 Bulk Water Supply to West Howrah Township 06-WS-CMA-13-1 Oct'2015 807.27   711.78 88.17 90.00  
10 Construction of approach road in the ESR (Panihati Municipality) 08/WS/CMA/3 Oct'2015 9.50 9.50 2.42 25.47 26.00  
11 Augmentation of 2.5 MLD SW Treatment Plant at Baranagar Municipality 08/WS/CMA/5 Sep'2015 385.00 287.76 205.61 53.40 80.00  
12 Augmentation of Water Supply at Baruipur Municipality 08/WS/CMA/7 Dec'2015 499.96 400.00 336.19 67.24 77.00 Delay due to non-availability of pipe.
13 Repair & renovation of Machineries, equipment's including Civil works of 30 MGD WTP at Padmapukur, Howrah 08/WS/CMA/8 Sep'2015 206.25 100.00 18.17 8.8 75.00  
14 Repair & renovation of 5 nos Old OHR under Naihati Municipality 08/WS/CMA/9 Oct'2015 113.42 113.42 0.00 0.00 80.00 Connection pending for non-availability of pipe.
15 Augmentation of Kalyani WTP 08/WS/CMA/10 Oct'2015 326.86 163.00 156.00 47.72 80.00  
16 Supply of Surface water Naihati Municipality 08/WS/CMA/11 Dec'2015 153.22 76.00 0.00 0.00 0.00 Delay due to non-availability of pipe.
17 Rejuvenation of 30 MGD WTP at BKTP 08/WS/CMA/13 Dec'2015 100.00 100.00 34.11 34.11 95.00  
18 Renovation of 2 nos ESR of Halisahar Municipality 08/WS/CMA/14 Dec'2015 43.44 43.44 0.00 0.00 50.00 As per request of ULB one no of ESR to be taken up after Puja Festival.
19 Beautification, renovation & other related works at Mullick Bari Guest house & campus 08/WS/CMA/15 Oct'2015 24.98 6.77 6.76 27.06 70.00  
20 Augmentation of existing Howrah Water Works located at Srirampur 08/WS/CMA/16 Dec'2016 999.00 0.00 0.00 0.00 0.00  