Water & Sanitation Sector

It will look after all the WS, Sewerage and drainage, disposal units, etc. as presentlearlier looked after by the WS, GAP, and SD & SWM Sector. All repair and maintenance work of such projects during the warranty period and thereafter as well may be taken care of by this sector.

Status of Water Supply Projects under Water Supply Sector, KMDA.

Sl no Name of the project Project code Date of Completion Project cost Fund received expenditure Financial progress % Physical progress % Remarks
JNNURM PROJECTS
1 Surface WS Scheme for Bally Municipality 07/WS/NURM-1/13 Partial commissioned 13849.36 11914.12 11407.06 82.36 74.57  
2 24x7 WS Scheme for Panihati Municipality, Kolkata U.A. 07/WS/NURM-1/14 Partial commissioned 24602.30 15109.76 14695.37 59.73 77.16 Delay due to non-availability of Way leave permission from Rly. Authority.
3 Trans municipal W.S. Project for municipal Towns of Madhyamgram, New Barrackpore and Barasat 08/WS/NURM-1/01 Feb'2016 44547.77 28405.83 24793.37 55.65 56.97 Delay due to non-availability of pipe
4 24x7 WS Project for Dumdum,SouthDumdum and North Dumdum 07/WS/NURM-1/10 commissioned 31272.08 28528.46 28523.61 91.21 90.34 Fund not received.
5 WS Scheme for Bhatpara Municipal Area 07/WS/NURM-1/12 Commissioned 24970.42 21633.41 19044.90 76.27 80.64  
6 Garulia Water Supply 07/WS/NURM-1/09 Commissioned 4719.26 4495.11 3959.47 83.90 93.79  
7 Integration of 30 MGD WTP at Kalyani for catering Gayeshpur, Kanchrapara, Naihati Halisahar & Kalyani. 07/WS/NURM-1/08 Commissioned 17398.11 17398.11 17252.25 99.00 99.00  
8 Water Supply Scheme for Bhadreswar Municipality 07/WS/NURM-1/13 Mar'2016 8877.28 2108.35 2061.61 23.22 29.80 Delay due to non-availability of Pipe
STATE FUND PROJECTS
9 Bulk Water Supply to West Howrah Township 06-WS-CMA-13-1 Oct'2015 807.27   711.78 88.17 90.00  
10 Construction of approach road in the ESR (Panihati Municipality) 08/WS/CMA/3 Oct'2015 9.50 9.50 2.42 25.47 26.00  
11 Augmentation of 2.5 MLD SW Treatment Plant at Baranagar Municipality 08/WS/CMA/5 Sep'2015 385.00 287.76 205.61 53.40 80.00  
12 Augmentation of Water Supply at Baruipur Municipality 08/WS/CMA/7 Dec'2015 499.96 400.00 336.19 67.24 77.00 Delay due to non-availability of pipe.
13 Repair & renovation of Machineries, equipment's including Civil works of 30 MGD WTP at Padmapukur, Howrah 08/WS/CMA/8 Sep'2015 206.25 100.00 18.17 8.8 75.00  
14 Repair & renovation of 5 nos Old OHR under Naihati Municipality 08/WS/CMA/9 Oct'2015 113.42 113.42 0.00 0.00 80.00 Connection pending for non-availability of pipe.
15 Augmentation of Kalyani WTP 08/WS/CMA/10 Oct'2015 326.86 163.00 156.00 47.72 80.00  
16 Supply of Surface water Naihati Municipality 08/WS/CMA/11 Dec'2015 153.22 76.00 0.00 0.00 0.00 Delay due to non-availability of pipe.
17 Rejuvenation of 30 MGD WTP at BKTP 08/WS/CMA/13 Dec'2015 100.00 100.00 34.11 34.11 95.00  
18 Renovation of 2 nos ESR of Halisahar Municipality 08/WS/CMA/14 Dec'2015 43.44 43.44 0.00 0.00 50.00 As per request of ULB one no of ESR to be taken up after Puja Festival.
19 Beautification, renovation & other related works at Mullick Bari Guest house & campus 08/WS/CMA/15 Oct'2015 24.98 6.77 6.76 27.06 70.00  
20 Augmentation of existing Howrah Water Works located at Srirampur 08/WS/CMA/16 Dec'2016 999.00 0.00 0.00 0.00 0.00  
Water Supply Projects

SD & SWM Sector

Objectives:
  1. The sewerage scheme shall improve the existing sewerage network, provide missing links in the planned city and shall provide a new network in the uncovered areas of the municipalities.
  2. The drainage scheme shall improve the hygienic condition of the people residing in the planned city to a considerable extent during the monsoon period.
  3. The storm water drainage scheme introducing new drains and establishing proper outfall systems, in order to improve the infrastructure facilities shall thereby provide relief from water logging in the KMA area.
  4. The Solid Waste Management Project includes a sustainable Regional Waste Management Centre clubbing a cluster of municipalities and comprising of sanitary landfill sites, leachate treatment unit and septic tank sludge treatment facilities. This RWMC will reduce contamination of ground water and will improve living, environmental and hygienic condition of the people of all municipalities against municipal waste.

    Besides RWMC, there is provision of (a) transfer station for segregation of inert (non - composite / non-bio-degradable) materials for transportation to landfill sites and recycled waste for selling and (b) provision of mechanical compost plant / vermicomposting for processing of organic waste to organic manure for selling.

List of Projects implemented under SD & SWM Sector during the last five years.

Project Project Cost
(amount in Lakh of INR)
Completion year
Storm Water drainage scheme in Hooghly-Chinsurah Municipality 3881.96 2011
Storm Water Drainage for Bidhannagar Municipal Area 1915.53 2011
Storm Water drainage for Bansberia Municipality 2979.36 2012
Storm Water Drainage Scheme in Budge Budge Municipal Area within Kolkata U.A 3480.16 2014
Storm Water Drainage for Baranagar Municipal area within Kolkata U.A 3587.39 2014
Integrated Storm Water Drainage System Project for Madhyamgram Municipality within Kolkata Metropolitan Area. 7204.37 2014
Integrated Storm Water Drainage System Project for Barasat Municipality within Kolkata Metropolitan 8548.33 2014
Storm Water Drainage Scheme for Kamarhati Municipality, Kolkata 6757.05 2015
Drainage and Sewerage Project in Bidhannagar, Kolkata 2358.45 2016
Storm Water Drainage Project for Baruipur Municipality 6401.74 2016

List of On going major projects under SD & SWM Sector

Project Project Cost
(amount in Lakh of INR)
Storm water drainage for Rishra Municipality 5107.31
Storm Water Drainage in South Dum Dum Municipality, Kolkata 6616.98
Intrgrated Drainage Scheme for Netaji Subhash Chandra Bose Airport. 6136.85
Kolkata Solid Waste management Improvement Project. (A JICA assisted project) for Uttarpara Kotrung, Konnagar, Rishra, Serampore, Baidyabati, and Champdani Municipality. 3584 Million JPY (INR 170.0 Crore)

Ganga Action Plan Sector

Chief Engineer: Shri B. Sengupta, Ph: 2337-1483

HIGHLIGHTS
  1. To reduce the pollution of river Ganga by means of sewage interception & diversion, sewage treatment plant, electric crematoria, low-cost sanitation & riverfront development
  2. 110 schemes completed under Phase-I at a cost of Rs. 186.13 crore covering 15 Class-I towns
  3. Phase-II programme already taken up covering 26 towns and two outfall channels at an estimated cost of Rs. 222.62 crore for 175 schemes. Rs. 89 crore already spent
List of Projects implemented under Ganga Action Plan Sector during the last five year
  1. Provision of preventive measures to cover a target population of about 2 million slum-dwellers throughout KMA
  2. Use of local HHWs working at the slum level to promote hygiene
  3. Maximum cost efficiency by utilizing the existing resources
  4. Community participation by engaging local people in planning, implementation and monitoring of the health programmes, etc.

The projects under phase - 1 of the Ganga Action Plan are almost complete. A summarized account of the number of projects in towns both within and outside Kolkata Metropolitan Area (KMA) is furnished below:

Town SEW STP Lcs Crema RFD Other Total
KMC 6 3 4 4 3 1 21
HMC 2 1 0 1 1 0 5
Municipal Towns within KMA 21 9 16 10 16 0 72
KMA Sub-Total 29 13 20 15 20 1 98
Municipal Towns outside KMA 2 2 2 2 4 - 12
Total 31 15 22 17 24 1 110

Some particulars of some of the major GAP schemes are noted below :

GAP schemes in KMC area
Garden Reach STP

Location: South Suburban, Garden Reach and Cossipore-Chitpur.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 16 I & D schemes with three main lifting stations and 3 STPs, one each of activated sludge process, oxidation pond method and trickling filter method, have been provided under the project.

GAP schemes in HMC area

Location: South and south west parts of Howrah.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 2 I & D schemes with two main lifting stations and 1 STP using trickling filter method, have been provided under the project.

GAP schemes in Bally municipal area

Location: Different areas within Bally municipality with STP at Kona in West Howrah.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 3 I & D schemes with one main lifting station and 1 STP using oxidation pond method, have been provided under the project.

GAP schemes in Titagarh Municipality

Location:Different areas within the municipality with a STP at Bandipur.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 4 I & D schemes with one main lifting station and 1 STP have been provided under the project.

GAP schemes in Bhatpara Municipality
Bhatpara STP

Location: Different areas within the municipality with STPs at Madrail and Jagaddal.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 6 I & D schemes with three main lifting stations and 2 STPs, one each of activated sludge process and oxidation pond method, have been provided under the project.

GAP schemes in Chandannagar Municipality
Chandannagar STP

Location: Different areas within the municipality with a STP at Khalisani.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 3 I & D schemes with one main lifting station and 1 STP have been provided under the project.

GAP schemes in Serampore Municipality

Location: Different areas within the municipality with a STP at Jannagar Road.

Objective: To intercept the sewage and then divert the same to STP for treatment and then discharging into the River Hooghly. For the purpose, 3 I & D schemes with one main lifting station and 1 STP with trickling filter method, have been provided under the project.

Material Sector